Thursday, December 31, 2015

More Exterior Walls and Truss Delivery

The exterior walls continue to go up.
   

Here's the trusses!

When the truck delivering the trusses backs into the power pole and the lines snap off and fall down, you need the nice people from the electric company to come out and put them back up. (Nobody was injured, thank God!)


Trusses everywhere! The crane is scheduled for 1/6 to set the trusses.

Monday, December 28, 2015

Exterior Walls

Thanks to the pre-fab, the exterior walls went up quickly.


I love this picture! Mom has the perfect view of the construction from one of her back bedrooms.

Tuesday, December 22, 2015

And Then It Rained!

After the slab was poured, we got a lot of rain. Steve set up production in his shop to pre-fab all of the walls that contain doors and windows.


Steve and I both checked out the lot to see if there were any problem areas. Just a little ponding. No problems!







Monday, December 21, 2015

Monolithic Pour

Today's the big day, concrete trucks are on site and more are on the way! It took nine trucks to do the house and 3-car garage. They ran out of daylight before they could get the camper garage done. They will do the camper garage, as well as the stamped concrete, at a later date. The front porch, patio areas, and breezeway are all going to be stamped concrete. Here's the pour:


 











Here's a short video of some of the pour (2:33):

And, just for the record, the plumbing drains were approved:

Sunday, December 20, 2015

What's In The Slab...

I arrived home in time to take final pictures before the concrete is poured. I wanted a record in case any work needs to be done in the future. The light wasn't the greatest when I arrived, but it will have to do... This is from the street, looking down the driveway. The camper garage is on the left. The house is on the right, with the side-load 3-car garage visible in this shot.

Here's what's in the slab...









Thursday, December 17, 2015

Ready For Concrete

We had some rain. I don't see any areas where it's caused any problems... There's a lot of rain in the forecast. The pour is scheduled for 12/21. Fingers crossed for nice weather!

Looking at the below picture, the camper garage is in the lower left hand corner. There's a breezeway between the garage and the house. The breezeway leads to a patio area -- turn right into the sunroom. From there you can go to Mom's on the right or my house on the left.

Camper garage.

Tuesday, December 15, 2015

Radiant Floor Heat

All of the insulation, rebar, and wire mesh is in place. The PEX piping for the radiant floor heat gets attached to the wire mesh so it stays in place. All of the blue and orange spray paint designates walls and cabinets, places where you don't want the PEX.


Sunday, December 13, 2015

Driveway

There's a large turn-around area in front of the 3-car garage.

Saturday, December 12, 2015

Insulation

Insulation goes between the ground and the slab. The area closest to the camera is Mom's house. The indented area is the sunroom that seperates Mom's house from my house at the far end. The bump out to the left is the pool room.

This is one of Steve's sons, working hard.

Thursday, December 10, 2015

More Drain Pipes Installed

It's coming together! A lot more drain pipes have been installed.


The camper garage is ready for concrete.

This is Mom's bathroom. Shower drain on the far right, toilet drain in the middle, sink drain on the far left.





The front porch goes the entire length of the front of the house. That's Mom's bathroom again closest to the camera.