Wednesday, December 9, 2015

More Preparation For The Slab

There is still a lot of work to be done before we are ready for concrete. There's rebar and wire mesh and insulation.

Tuesday, December 8, 2015

Preparing For The Slab

The plumber had to come in and put in the drains. Rebar and wire mesh will need to be installed. Insulation goes between the ground and the slab.

This is the camper garage.

The house behind me to one side is up on a hill.



Friday, November 27, 2015

More Pictures Of Framing The Footers

This was what was happening when I was home for Thanksgiving.


This is from the back corner of the garage looking toward the street.

This is from behind my house looking toward the street.

Tuesday, November 24, 2015

Framing The Footers Day 2

It's starting to take shape!



The part that goes deep to toward the woods is the side load 3 car garage.

This is looking at the back of the garage toward the street.


Framing The Footers

Construction of the framing to pour the footers started yesterday 11/23.

Saturday, November 21, 2015

Digging The Footers

They dug the footers today, 11/21. This is facing north, with the street on the right.

Facing northwest.

Facing north.

This is the same guy that dug the holes for the perc.

Preparing For The Slab

Yesterday (11/19) they brought in truck-load after truck-load of bankrun to prepare for the slab. This is looking north. The street is on the right.

This is facing south. The road is on the left. That's Mom's house beyond the white truck.